LOTUS cooperated with the Kenya Government to provide the total solution of the construction site for pipeline from Nairobi to Mombasa to occupy 400 workers, including the office,accommodation, canteen and etc. with furniture by using the Flat-Pack containers, and also the infrastructure on site. LOTUS was in charge of every process from communicating to planning, to designing, then to producing, transporting and assembling on site.

Planning & Designing: 20 days
Production: 30 days
Transportion: 30 days
Assemble: 45 days